ANC6B Transportation Committee Hears from DDOT on Sidewalk Repair

ANC6B Transportation Committee Hears from DDOT on Sidewalk Repair

by Larry Janezich and Barbara Riehle

Wednesday night, Aaron Rhones, DDOT Program Manager for Traffic Safety, was on hand at Commissioner Oldenburg’s ANC Transportation Committee to talk about sidewalk repairs. He is in charge of a new approach to managing repairs called “CityWorks,” and his purview includes street repairs, sidewalks, alley and trees.  Currently Rhones is working on completing a backlog of requests for repairs citywide, 722 in Ward Six alone.

According to Rhones, under the new “City Works” program, the response system has been streamlined and improved.  The best way to get service, he says, is to call 311 or file a request online with the call center. The complaint gets a number which can be tracked by Rhones’ department.  Residents can also enlist the aid of their ANC representative.  Rhones agreed to provide ANC6B with a prioritized list of the 722 Ward 6 projects, and it’s likely the ANC will weigh in with their own take on prioritization in 6B. 

Mr. Rhoens expects all 722 Ward 6 projects to be competed in 2012. The citywide budget for sidewalks is between $2-2.5 million annually.  Given the limited size of the DDOT sidewalk budget, Commissioner Brian Pate raised the possibility of using Performance Parking Funds for repairs, which apparently would meet the program’s criteria that projects by non-vehicular and transportation-related.

Comments Off on ANC6B Transportation Committee Hears from DDOT on Sidewalk Repair

Filed under Uncategorized

ANC6B Likely To Back Plan to Alleviate Police Parking Issues at Marion Park Substation

ANC6B Likely To Back Plan to Alleviate Police Parking Issues at Marion Park Substation

 by Larry Janezich and Barbara Riehle

A new parking plan for E Street between 4th and 6th Streets, SE on the northern side of Marion Park looks certain to receive the endorsement of ANC6B at next week’s December meeting. 

The plan, worked out between residents and police officials by Commissioner Norm Metzger, anticipates that parking on the south side of E Street would be restricted 24/7 to police parking only.  Zone 6 residential parking along the north side of E Street between 4th and 6th Streets will be extended, 7:00 am until midnight, seven days a week.  Police would not be permitted to park their personal or MPD vehicles in these residential spaces on D and E Streets.

The proposed changes would become permanent after a trial period, if the new plan successfully resolves the frictions between the MPD and Substation neighbors.  These frictions – double parking, difficulties for resident parking, blocked cars,  etc., are especially acute during shift changes, according to a draft letter from ANC6B to DDOT’s Transportation Operations Administrator, Damon Harvey.

The next meeting of ANC6B will be Tuesday, December 13, 7:00pm at The Hill Center.

1 Comment

Filed under Uncategorized

Mt. Joy Baptist Church Condo Project Gets First Hearing before CHRS Committee – Developer Seeks Historic Preservation Approval

Rendering of Restored Facade of Mt. Joy Baptist Church

Mt. Joy Baptist Church Condo Project Gets First Hearing before CHRS Committee – Developer Seeks Historic Preservation Approval  

by Larry Janezich

Monday evening, Altus Real Estate principal Charlie Kehler and representatives of Cunningham and Quill architects, appeared before the Capitol Hill Restoration’s Society (CHRS) Historic Preservation Committee, the first step in getting approval for the historic preservation application for conversion of Mt. Joy Baptist Church and adjacent townhouse into 12 condo units.  The developer and architect team is also converting The Maples – formerly Friendship House – into residential units, a process currently underway. 

The familiar white painted façade of the Church and townhouse at 514 4th Street, will be stripped to the original mid-19th Century brick, and restored to their original appearance, with no major changes to the historical aspects of the structure, though a utilitarian addition at the rear of the church dating to the early 20th Century will be removed. 

There will be a total of 10 condos in the former church and two in the adjacent townhouse.  The project will provide 6 to 10 underground parking spaces (probably 6) in the church.  Residents in units without underground parking will use street parking – less impact, the architects point out – than regular parking by a 300 member congregation. 

Each of the condos will have two bedrooms, with the largest unit on the church’s third floor spanning the width of the building and overlooking 4th Street.  This unit will benefit from all three of the arched windows on the building’s front.  The architects predict that construction will take about a year and is tentatively scheduled to begin in the fall of 2012.   

The developer and architect are scheduled to appear before Commissioner Francis Campbell’s ANC6B Planning and Zoning Committee on Tuesday, December 6, at 7:00pm at St. Coletta’s School, 1901 Independence Avenue SE.  The full ANC6B will consider the application at their regular meeting on Tuesday, December 13, at 7:00pm at The Hill Center.  The historic preservation application goes before the Historic Preservation Review Board (HPRB) on December 22.

The CHRS Historic Preservation Committee is chaired by Nancy Metzger, whose nomination to the Historic Preservation Review Board by Mayor Gray was announced last month.  Metzger is also active with the Historic Districts Coalition.  Her nomination was endorsed by the Committee of 100, but not the D.C. Preservation League or the DC Business Industry Association (DCBIA).  DCBIA is the main non-profit trade association representing the real estate development industry in the District of Columbia. 

Altus Realty Management is an Arlington-based firm that provides brokerage services and property and construction management.  The firm is headed by Terry Hindermann and Charlie Kehler, both listed as principals on the company website.

Comments Off on Mt. Joy Baptist Church Condo Project Gets First Hearing before CHRS Committee – Developer Seeks Historic Preservation Approval

Filed under Uncategorized

Forecast for ANC6B

Forecast for ANC6B

by Larry Janezich

8th Street Pizza

Steve Salis, the entrepreneur who hopes to open up a gourmet pizza place in the space formerly occupied by China Wall, may still have some heavy lifting to do before getting ANC approval.  He’ll have to find a way around the moratorium on fast food places on Barracks Row, despite what appears to be community enthusiasm for the new pizza place with gluten free options.  It’s not yet clear when the proposal will come before the ANC. 

Eastern Market Governing Authority Legislation 

ANC6B will announce a date soon for a Special Call meeting on proposed Eastern Market governing authority legislation.  The date will likely be December 19th in the Peoples Church, contingent on approval of parties involved.  ANC6B Commissioner Brian Pate is drafting a resolution of recommendations to be brought before the ANC and the community which he expects to make public on December 12th.   The legislation is not likely to be taken up by the City Council until January. 

iGaming

Look for ANC6B to come out in opposition to DC government sanctioned iGaming (internet gambling) within DC at its next meeting on Tuesday, December 13.  The City Council sees this as a revenue-enhancing measure to ease budget shortfalls.  The need for cash is a hard argument to overcome.  

Hine Zoning Subcommittee Website

ANC6B’s Subcommittee on the Hine Rezoning process (PUD) is planning to launch a website to distribute information and possibly elicit community feedback. 

18th Amendment Sidewalk Cafe

ANC6B will have another crack at the application of the 18th Amendment for a sidewalk café.  The ANC’s feathers were ruffled when the DOT Public Space Committee granted the restaurant a permit for a sidewalk café without running it by the ANC.  However, the fact that the restraint’s voluntary agreement with the neighbors will have to be amended by the Alcohol Beverage Review Administration (ABRA) gives the ANC an opportunity to weigh in with an opinion.  That will happen first on this coming Thursday before the ABC Committee which will meet in The Hill Center at 7:00pm.

Comments Off on Forecast for ANC6B

Filed under Uncategorized

7th Street Wine Bar to Open by Month’s End – Exclusive Photo

Boxcar, Across from Eastern Market, Will Open Later this Month

7th Street Wine Bar to Open by Month’s End – Exclusive Photo

by Larry Janezich

Boxcar, Xavier Cervera’s new wine bar, across from Eastern Market in the space once occupied by Petite Gourmet, is scheduled to open by the end of December, according to Cervera.  Named, perhaps, for the room’s long narrow shape, the new bar is the latest in a growing list of Cerverea’s Capitol Hill bars and restaurants including, Lola’s, Molly Malone’s, The Chesapeake Room, and Senart’s.  Also being added to the list is the old Hawk & Dove which Cervera purchased earlier this year and which has been completely gutted for renovation.

3 Comments

Filed under Uncategorized

Eastern Market Report – New Rules Coming for North Hall

Eastern Market Report – New Rules Coming for North Hall

by Larry Janezich

North Hall

At Wednesday’s meeting of the Eastern Market Community Advisory Committee (EMCAC), Market Manager Barry Margeson announced that a full time manager for the Market’s North Hall has been hired to schedule and manage events in the facility.  The North Hall manager will have an office in the North Hall in space previously reserved for use of caterers.  Margeson also said part of the new manager’s responsibility will be to “curb excessive use” of the hall by nannies and children who congregate there during the day on a regular basis.  He said that new rules governing the day time use of the Hall will be forthcoming.  Members of EMCAC have recently expressed concern regarding liability issues for the new governing authority, as well as excessive wear and tear occasioned by use of the facility as an unrestricted play zone.   

New Governing Authority for the Market

Vendors, farmers and merchants are still grumbling about the as-introduced version of the legislation put forward by Councilmember Wells to create a new governing structure for the Market.  They feel the measure does not protect their rights regarding grandfathering and right of first refusal.  “Grandfathering” refers to protecting the status of those vendors and merchants who were with the market when the last legislation governing the market was passed in 1997.  “Right of first refusal” refers to those vendors and merchants who have come to the Market since 1997 but have been there long enough to deserve protection. 

The timeline for passing the bill has been pushed back into the new year, allowing additional time for meetings and stakeholder input, and it seems likely that some of these concerns will be addressed before the bill is finalized.  A meeting of EMCAC’s Committee of the Whole to consider final recommendations on changes to the legislation will be held Tuesday, January 3 at 7:00pm in North Hall.  The meeting will be open to the public but since it is a working meeting, there will be no opportunity for public comment.   (An article on EMCAC’s discussion of possible changes to the legislation will be posted this weekend.) 

Rent Increase for Farmers and Vendors

As of December 1, rent increases for the farmers and food vendors who work outside the market went up 10 percent.

The new rates for farmers and food vendors range from $30 a day for a tent to $44 a day for a bay beneath the farmer’s line shed.  For non-food vendors,  rates run from $28 a day to $44 a day, depending on location. 

EMMCAC’s next regular meeting will be on December 28.

3 Comments

Filed under Uncategorized

Councilmember Wells’ Changes to Ward Six Redistricting Plan Get Solid Backing From Ward’s ANC Commissioners and Fengler

Councilmember Wells’ Changes to Ward Six Redistricting Plan Get Solid Backing From Ward’s ANC Commissioners and Fengler

by Larry Janezich

The City Council heard on Tuesday, November 29, from all Ward Six ANC Commissioners and Ward Six Redistricting Task Force Chair Joe Fengler (the latter by proxy) that the commissioners and Fengler had lined up solidly behind Councilmember Wells’ amendments to the Ward Six Task Force Redistricting plan. 

For ANC6B, this means united support from all quarters for the plan which would leave East Capitol Street as the northern boundary of ANC6B, eliminating the threat that ANC6C’s southern boundary would be extended to Independence Avenue between 7th Street and the Capitol Building.  Last fall, residents in the affected area had mounted an intense campaign to stay within ANC6B. 

The united front increases the likelihood that the Redistricting Subcommittee – comprised of Chair Michael Brown, Councilmember Jack Evans, and Councilmember Phil Mendelsohn – will back Wells’ plan. 

The City Council left the official record open until December 9th, after which the door will close on public comment.  The three members of the Subcommittee will then “take stock” and hold a public “mark-up” session during the week of December 12.  At that meeting, the Subcommittee will introduce and consider their recommendations for the Ward and ANC single member district boundary changes. 

The first reading of the bills to set the new boundaries before the City Council will occur on December 20.  Under DC law, the second reading and final passage of the bill to set the Ward boundaries must occur before the end of December.  The law requires boundaries of single member districts to be set by the end of January, so second reading and final passage of that bill will occur after the New Year.

Comments Off on Councilmember Wells’ Changes to Ward Six Redistricting Plan Get Solid Backing From Ward’s ANC Commissioners and Fengler

Filed under Uncategorized

Deputy Mayor’s Office Cited Misleading Data Justifying Award to Hine Developer – FOIA Permits Closer Look at Manufactured Consensus for Stanton’s Hine Development

Site of Proposed Development

Deputy Mayor’s Office Cited Misleading Data Justifying Award to Hine Developer – FOIA Permits Closer Look at Manufactured Consensus for Stanton’s Hine Development

by Larry Janezich

In a June 2010 email, Corey Lee, Deputy Mayor’s Office of Economic Development (DMPED) Project Manager for the Hine Jr. High development, listed community support as one of the five reasons the contract was awarded to Stanton-Eastbanc, i.e., “(v) the large amount of community support (none of the ten (10) teams documented more community support for its project than S-E).”

A Freedom of Information Act request reveals that, indeed, the Stanton/Eastbanc team garnered 119 emails of support during the public comment period, which ran from June through August of 2009, while its closest competitor, the Menkiti/Streetsense/DSF team, had only 34.

Yet a closer look at those emails supporting Stanton shows some startling results.  Of the 119 letters, 74 were form letters.  More troubling, research demonstrates that most emails, whether form letters or not, were written by someone who had a conflict of interest – realtors who work alongside one of the principals of Stanton Development, business associates, tenants, family members, or friends of the family.  But the Deputy Mayor’s Office solicitation of public comments required no disclosure of such conflicts, and in all cases but five no disclosure was given.  Nor was a supporter required to give an address; several letters supporting Stanton were written from outside Capitol Hill, or even outside the District of Columbia.  While the Deputy Mayor’s Office cited “documented” community support as one of the reasons it selected Stanton/Eastbanc, the office had no resident or conflict of interest screening mechanism by which to judge the letters of support that it received. 

If the pool of emails – both form letters and original letters – in support of Stanton is narrowed to those without a known business or personal connection to the developer and to those sent by Capitol Hill residents, then the support for Stanton is reduced to 28 letters, compared to 34 for Streetsense, all of which came from Capitol Hill residents, and none with obvious conflicts of interest.  To tally these results, each person whose name appeared on a letter in support of a developer was counted as one vote, regardless of the number of emails sent. 

As many readers will remember, the process of selecting a developer for the Hine project became controversial on June 17, 2010, with the endorsement of Stanton-Eastbanc by the CHRS on a perfunctory and nearly unanimous voice vote (there was one abstention) of the CHRS Board, without questions or debate, and based on the recommendation ad hoc committee comprised of a few board members.  (Then-Councilmember Kwame Brown subsequently said publicly that it was the CHRS decision which was the deciding factor in his vote for awarding the contract to Stanton.)  The first form letter supporting Stanton was sent to the Deputy Mayor’s office earlier that same day, originating with a Stanton business neighbor.  This first wave of support for Stanton was seemingly aimed at influencing the upcoming June 30 ANC6B vote on recommending a developer, since the letters in this first wave – both form letters and unique letters of support – copied ANC6B Commissioner Mary Wright (in whose Single Member District the project lies), and ANC6B Chair Dave Garrison. 

When the ANC met on June 30 in a small, overcrowded room in the Old Naval Hospital, it heard from the community members.  By the end of the meeting, it was clear that a strong majority of those present favored the StreetSense proposal.  The Commission avoided making a recommendation, and instead voted for a series of criteria which should be met by whichever developer was awarded the project.    

Following this public show of support in favor of Streetsense, between July 4 and July 10, a blizzard of form letters in support of Stanton arrived at the Deputy Mayor’s office inbox, no longer copied to ANC Commissioners.  The first of this second wave of form letters starts on July 4, from family friends of the developer.  Another set of form letters begins on July 6 from a realtor associated with the one of the principals of Stanton Development; this set is copied to the entire city council. 

Developers often have ties and relations to certain commercial or community interests, and it may well be that enumerating these connections provides a useful indicator or measure of something.  Whatever that something is, it is not community support.  Community members unfettered by conflict of interest issues have a role in naming their preferences among the finalists, whether as individuals or local groups.  This role extends to noting components of a design that spell trouble, and asking for benefits in return for the negatives the project brings to the community, including more crowded neighborhoods and streets.  

Almost a year ago, Capitol Hill resident Kathleen Frydl requested a meeting with the Deputy Mayor’s Office to discuss how it assesses community support since the selection of Stanton, but to date, the Office has not scheduled the meeting.

“I think a distinction needs to be drawn between documenting community connections,” Frydl says, “versus documenting community support.”  The former might be impressive, she notes, but compromised by sufficient conflict of interest questions so as to reduce the value of the input given.  “While it may be insightful and it may be heartfelt, input from people with a financial or personal relationship to the developer is just not the same as input spontaneously given by a neighbor who reviews the plans,” she said.  Frydl also believes that an open-ended and unscreened process might be the District’s preference, but, if so, she thinks that the Deputy Mayor’s Office should not rely upon it as a mechanism to help select a winning bid. 

On November 23, Stanton-Eastbanc filed an application for a Hine Planned Unit Development with the city’s Office of Planning.  That initiates a process under which a final design for the development will be agreed upon and amenities granted to the community to compensate it for the increased density the project will bring to the community.  The Office of Planning is organized under and reports to the DMPED, but as a practical matter it operates as a separate agency. 

DMPED tracks the project for the Mayor and, as the facilitator for the original Land Disposition and Development Agreement (LDDA), interprets the terms of the agreement on behalf of the Mayor.  In this sense, DMPED will likely continue to be a key stakeholder in the process, especially regarding definition of terms.

In this PUD process, the community will be represented to the Office of Planning and the Zoning Commission by a Subcommittee of ANC6B’s Planning and Zoning Committee.  The Subcommittee includes resident members representing CHRS, EMCAC, CHAMPS, EMMCA, Eyes on Hine, and the Eastern Market North Neighbors Association.  CHRS is participating with the understanding it will seek separate party status in the final hearing before the Zoning Commission, which will give it special status, time for a lengthier presentation, and the ability to call expert witnesses in support of its position.  In the last PUD process CHRS participated in, the group negotiated an $83,000 mitigation for the demolition of twelve historic buildings in the way of the new Dreyfuss development on H Street, NE.  CHRS then used those funds to conduct a survey for its “Beyond the Boundaries Project,” for the purpose of facilitating the expansion of the Historic District. 

Subcommittee Chairman Ivan Frishberg has stated that it is not the Subcommittee’s intent to preclude any organization from seeking party status, but rather to strengthen the ANC position in negotiations with Stanton-Eastbanc and the Office of Planning. 

CHRS will host a meeting for Stanton-Eastbanc to present its latest plans to the public on December 12.  The next meeting of the Subcommittee will be on December 14.

16 Comments

Filed under Uncategorized

Stanton-Eastbanc Files Application For Planned Unit Development on Hine Project – Latest Drawings For Hine Development Released

View of North Building from C Street, Looking North

View from 8th Street, Looking West

View from 8th Street, Looking West

View from 7th Street, Looking East

View from Pennsylvania Avenue, Looking North, Showing Height in Relation to Adjacent Buildings

View from Pennsylvania Avenue, Looking North

Stanton-Eastbanc Files Application For Public Unit Development on Hine Project – Latest Drawings For Hine Development Released

By Larry Janezich

Stanton Eastbanc filed an application for a Public Unit Development on the Hine Development on Wednesday, November 23.  Included in the document are the latest architectural renderings for the project.  To download an electronic copy, please click on the following or copy it to your browser address line. 

https://www.yousendit.com/download/T2dlb2VPdzh0QTJLRmNUQw

Since it is a large file it may take several minutes to download.

Comments Off on Stanton-Eastbanc Files Application For Planned Unit Development on Hine Project – Latest Drawings For Hine Development Released

Filed under Uncategorized

Thanksgiving Day Morning, 2011

Eastern Market, 8:25am, Thanksgiving Day

Eastern Market Metro, 8:30am, Thanksgiving Day

Pennsylvania Avenue, 8:30am, Thanksgiving Day

Comments Off on Thanksgiving Day Morning, 2011